D-16 Sample Migration Task Lists
Cutover Migration Task List Example Adaptive Server Enterprise 11.5
Front-End Regression Test Suite
1. Perform user regression testing.
2. Monitor and capture system dynamics (
sp_who, sp_lock...).
3. Verify and document Adaptive Server 11.5 regression test.
Other Testing
Verify 11.5 performance and functions on the test system.
Run User/Acceptance Tests on the Release 11.5 Test System
1. Testers perform user regression testing of Release 11.5.
2. Monitor and capture system dynamics (
sp_who, sp_lock...).
3. Verify and document the Release 11.5 regression test.
4. Make the Release 11.5 “go/no go” decision for the production
system.
Execute Release 11.5 to 10.x Fallback Procedures on Test System
1. Shut down the Release 11.5 test system.
2. Re-create the Release 10.x test system.
3. Re-create the Release 10.x environment, using your re-creation
scripts and procedures.
4. Load the Release 10.x production system dumps.
5. Run
dbcc commands (checktable,checkalloc, checkcatalog) on the Release
10.x databases. Be sure to verify the
dbcc log and error log.
6. Run
checkpoint on the Release 10.x test system.
Upgrade Production Server from Release 10.x to 11.5
1. Perform a dump of Release 10.x databases on the production
system.
2. Before the upgrade, run
dbcc commands (checktable, checkalloc,
checkcatalog).
3. Alter the sybsystemprocs database.
4. Perform a pre-upgrade verification.
Comentarios a estos manuales