Migrating to Sybase Adaptive Server Enterprise 11.5 D-15
Adaptive Server Enterprise 11.5 Cutover Migration Task List Example
Front-end Regression Test Suite
1. Perform regression testing for local team.
2. Monitor and capture system dynamics (
sp_who, sp_lock...).
3. Make the “go/no go” call for the Release 10.x test system.
4. Verify and document this SQL Server 10.x regression test.
5. Verify performance and functions on the test SQL Server 10.x.
Upgrade Release 10.x Test System to Release 11.5
1. Perform a dump of the Release 10.x databases.
2. Before the upgrade, run
dbcc commands (checktable, checkalloc,
checkcatalog).
3. Alter the sybsystemprocs database.
4. Perform a pre-upgrade verification.
5. Upgrade the test system to Release 11.5.
6. Run
dbcc commands (checktable,checkalloc, checkcatalog) on the Release
11.5 databases. Be sure to verify the
dbcc log and error log.
7. “Baseline” the Release 11.5 configuration.
Run Regression Test Suites on Release 11.5 Test System
Recycle Adaptive Server before starting tests.
Back-End Regression Test Suite—Production Loads
1. Iteratively perform the back-end regression testing.
2. Monitor and capture system dynamics (
sp_who, sp_lock, statistics io...).
3. Verify and document Adaptive Server 11.5 regression test.
Front-End Simulation Regression Test Suite
1. Perform front-end simulation regression testing.
2. Monitor and capture system dynamics (
sp_who, sp_lock...).
3. Make the “go/no go” call for the 11.5 system.