Parallel Migration Task List Example
120
• Define Test/Acceptance Criteria—Regression Test Suites
• Set Up Target Production Environment
• Set Up Replication Server
• Run Regression Test Suites
• Upgrade Server B (Shadow)
• Run Post-upgrade Regression Test Suites on ASE 12.5 (Server B)
• Run User Acceptance Tests on ASE 12.5 (Server B)
• Shift Production Users to Adaptive Server 12.5 (Server B)
• Perform Final Steps
Define Test/Acceptance Criteria—Regression Test Suites
Back-end regression test suite—production loads
1 Identify back-end queries.
2 Encapsulate back-end queries.
3 Create back-end test suite (
showplan, stat io, and stat time wrappers).
Front-end simulation regression test suite
1 Identify target user functions.
2 Capture and map SQL for target user functions.
3 Encapsulate SQL for user functions.
4 Create front-end simulated test suite (
showplan, stat io, and stat time
wrappers).
Front-end Phase 1 and 2 regression test suite
1 Identify front-end test scenarios.
2 Review front-end application and acceptance/test procedures.
3 Document functional test approach.
4 Compose front-end test mix matrix.